Department: Public Works and Infrastructure
           Payment  for Capital Assets decreased from R26.387  million in 2019/20 to a  revised estimate of
           R20.131 million. In 2023/24, budget increases by 4.2 per cent to R20.981 million when compared to the
           2022/23 revised estimate due to continued provision to replace the ageing ICT equipment.

           8.2  Programme 2: Public Works Infrastructure

           Objectives: To provide a balanced and equitable provincial government building infrastructure by
           promoting accessibility that is sustainable integrated and environmentally sensitive, which supports
           economic development and social empowerment. The programme is divided into 7 sub-programmes as
           follows:
           x    Programme support: To manage the activities of the professional components strategically as well
                as to render an administrative support services to the professional components with regard to finance
                matters and supply chain management;
           x    Planning: Manages the demand for infrastructure development monitoring and enforcement of the
                built sector as well as property management norms and standards;
           x    Design: Designs new and upgrade building infrastructure with the intention to ensure that plans are
                ready for funding and will include only 4 of the 6 procab stages (namely stages 1 to 4 of project
                inception, concept design, development and projects documentation, respectively);
           x    Construction: Responsible for new construction upgrading and refurbishment and it entails 2 of the
                procab stages (namely stage 5 of construction period and contract administration and stage 6 of
                project close out and debriefing);
           x    Maintenance: Responsible mainly for  four maintenance activities namely: routine  maintenance,
                scheduled maintenance, alterations and conditions assessment of all buildings;
           x    Immovable Asset Management:  Manages the property portfolio of the province by establishing and
                managing the provincial strategic and infrastructure plan to provide accommodation for all provincial
                departments and other institutions as well as acquire and dispose of accommodation in terms of the
                plans; and
           x    Facility Operations: Manages the operations of buildings (including facilities management, cleaning,
                greening, beautification, interior decoration and designs, and day to day preventative maintenance of
                electronic, electrical and mechanical equipment) and all services related to managing a building.

           Table 13: Summary of departmental payments and estimates sub-programme: P2 – Public Works
           Infrastructure


                                                         Main    Adjusted
                                       Outcome                          Revised estimate  Medium-term estimates  % change from
                                                        appropriation  appropriation                        2022/23
            R thousand         2019/20  2020/21  2021/22          2022/23          2023/24  2024/25  2025/26
            1. Programme Support                  107 048                 121 710                 158 570                 159 792                 154 221                 183 568                   67 594                   43 707                   11 968  (63.2)
            2. Planning           4 257    4 122    5 186   7 315    5 575   5 575    1 179   2 365      2 147  (78.9)
            3. Design               –        –       –        –        –       –        –       –          –
            4. Construction                   288 713                 193 933                 250 193                 290 153                 267 030                 201 357                 308 578                 323 700                 340 852  53.2
            5. Maintenance                   187 902                 174 079                 174 754                 178 278                 188 687                 189 021                 226 061                 229 044                 237 981  19.6
            6. Immovable Asset Management                   933 924                 991 711               1 014 184               1 020 469               1 110 340               1 143 080                 965 854               1 038 597               1 070 999  (15.5)
            7. Facility Operations                  234 453                 264 498                 252 605                 277 098                 296 798                 296 798                 314 941                 334 000                 345 459  6.1
            Total payments and estimates                1 756 297               1 750 053               1 855 492               1 933 105               2 022 651               2 019 399               1 884 207               1 971 413               2 009 406  (6.7)






















                                                             277